Timeline

  1. 01.
    July 2023

    EIA Screening

  2. 02.
    September - October 2023

    Community Consultation

  1. 03.
    November / December 2023

    Potential planning application submission to Eastbourne Borough Council

    In Progress
  2. 04.
    Winter 2023/24

    Borough Council will consider and determine the application

    In Progress
  3. 05.
    Summer 2025

    Earliest commencement of construction (if planning permission is granted)

    In Progress

Additional Information

We have now submitted a full planning application to Eastbourne Borough Council (application reference number: 230800). Please find the link here: https://www.lewes-eastbourne.gov.uk/article/2087/?RefType=APPPlanCase&KeyText=230800